Current Road Works: Mon, 16 Aug 2021 – Sun, 22 Aug 2021

Infra Weekly Road Works Notice: Mon, 16 Aug 2021 – Sun, 22 Aug 2021

Motorists, pedestrians and residents are asked to proceed in the following work areas with caution and follow the directions of the traffic wardens.

 

Rock Hall, St Lucy

Milling and Paving scheduled to start this week in Rock Hall, St Lucy. Work will be carried out between 7:30am and 4:30pm and is expected to be complete by the end of August.

While roads will remain open, motorists are asked to follow the road signs and wardens. 


Malvern Tenantry, St John

Milling and Paving are scheduled to start this week in Malvern Tenantry, St John. Work will be carried out between 7:30am and 4:30pm and is expected to be complete by the end of August.

While roads will remain open, motorists are asked to follow the road signs and wardens. 


Bank Hall, St Michael

Milling and tack coat to Leinster Road will continue this week.


Bridge Cot, St George

Road works in Bridge Cot, St George, from Rubis Service Station to Highway 3B will continue this week for the installation of a concrete curb and slipper on both sides of the road.

While the road will remain open to vehicular traffic, residents and motorists are asked to follow the directions of traffic wardens and plan their routes accordingly.

Work will be carried out between 7:30am and 4:30pm and is expected to be complete by the end of August.


Complete:

  • Whitehall Main Road, St Michael
  • First Ave, Vauxhall, Ch Ch
  • Bank Hall, St Michael
  • Rock Gap #1 and #2, St Michael


Thank you for your cooperation as we carry out these maintenance works on our public infrastructure, and apologise for any inconvenience caused during this time.

 